Sunshine Sugar Site Shut Down

Scope

  • Berg were engaged to perform multiple jobs while onsite at Yamba sunshine sugar mill.
  • Shut down duration spanning from 27/03/2023 to 14/06/2023.
  • Berg supplied 4-5 boiler makers and 3-4 fitters on site during the shutdown.

Boiler Makers

  • Berg were engaged to repair and replace structural sections of buildings and flooring throughout the site. Various head chutes on numerous conveyor systems repaired and bought back to a safe secure standard. Boiler tubes blanked off and welded, guards remanufactured and installed. Many parts made as required in sunshine sugars onsite workshop.

Fitters

  • Berg fitters onsite were required to strip and assess several pumps, replace bearings, replace belts. Remove and replace gland packing, maintenance on pullies and drums realign and tension belts. Replace scrappers on return belts.

Work Completed

Damaged boiler tubes pressure vented blanked and plug welded.

Structural columns removed and repaired in damaged sections.

Chutes repaired and replaced as requested by sunshine sugar.

Flooring removed and replaced in many areas of the plant due to being unsafe for walking. In control rooms and up and down 6 conveyor systems.

Head chutes repaired and replaced.

Just a few snap shots of some of the work undertaken by Berg during the Sunshine Sugar shut down.

Client

Sunshine Sugar

Industry

Food & Beverage

Workshop

Onsite / Brisbane

Services

Project Management, Insitu Fabricating and Welding, Pump Removal Strip, access and overhaul Alignment of Pumps & Gearboxes Refurbishment of Pumps & mechanical equipment, Repair Boiler tubes, Repair/replace of sheets